Permits and approvals
This page covers the bureaucratic part: what has to be approved, by whom, in what order, and what we need from you. Durations and fees appear here only once confirmed — we do not invent numbers.

Work that requires design and approval
New construction and reconstruction under a building permit
Increase of allocated electrical capacity or a new connection
Gas connection and boiler room installation
Water and sewer connection or an increase in demand
Installation and upgrade of fire protection systems
Change of use: apartment → office, office → medical room, retail → restaurant
Layout changes that relocate wet zones or shafts
Equipment on the façade: condensers, extracts, kitchen ductwork
Process stages
Each stage ends with a specific document, not a status.
Collect baseline data
Public registry extract, existing technical conditions, architectural plans, building function and operating profile.
Preliminary load calculations
Electricity in kW, water in m³/day, heat in kW. These figures go into the utility applications.
Applications for technical conditions
Filed in parallel with electricity, water and gas companies so waiting periods do not stack up.
Architectural approval
The urban development service in Tbilisi or the relevant municipal service in the regions.
Fire section
Review of suppression, detection and smoke control together with the evacuation scenario.
Closing comments
We amend the documentation and resubmit. The log shows which comment was closed and when.
Installation and supervision
Hidden-works records, material certificates, change tracking for the as-builts.
Testing and handover
Balancing and test records, the final documentation set and acceptance by the commission.
What we need from you
Title document or lease agreement
Public registry extract and site plan
Architectural plans in dwg or pdf
Existing technical conditions if the building is already connected
Process brief: equipment, kitchen layout, medical devices
Power of attorney for filing applications
Authorities and requirements
The table is a reference. Durations and fees depend on the building and are filled in at project start.
Urban development service (Tbilisi) / municipality
What is approvedBuilding permit stages, façade interventions
What we need from youTitle, registry extract, architectural set
Technical and Construction Supervision Agency
What is approvedSupervision of construction activity, handover into operation
What we need from youRecords of completed works
Telasi (Tbilisi)
What is approvedTechnical conditions for connection or capacity increase
What we need from youLoad schedule, title, application
Energo-Pro Georgia (regions)
What is approvedConnection and allocated capacity outside Tbilisi
What we need from youSame package for the site address
Georgian Water and Power (Tbilisi)
What is approvedWater and sewer connection, demand increase
What we need from youWater demand calculation, plans
United Water Supply Company of Georgia
What is approvedWater and sewerage in the regions
What we need from youSame package
Tbilisi Energy / SOCAR Georgia Gas
What is approvedGas connection, boiler room
What we need from youGas demand calculation, boiler room layout
Emergency Management Service (MIA)
What is approvedFire section and evacuation scenario
What we need from youBuilding function, occupancy, plans
Can allocated capacity be increased on an operating building?
Yes, by application to the utility. We recalculate the balance first — if the peak can be reduced, an increase is often unnecessary.
Is a design required for a layout change that moves wet zones?
Yes. Drainage falls and waterproofing change, and that is a liability question towards neighbours.
Who is responsible for fire certification?
The designer for the design solution, the installer for workmanship, the owner for operation. All three links are documented.
How long does permitting take?
It depends on the authority and completeness of the documentation.
Can construction start before technical conditions?
It happens, but it is risky: a capacity or demand limit can change the entire scheme.
Do you handle correspondence on our behalf?
Yes, under power of attorney. Decisions and signatures stay with the client.
What if an authority issues a comment?
We amend and resubmit at our cost when the comment concerns our scope.
Do you work outside Tbilisi?
Yes. In the regions the utility companies and municipal service change — we account for that in the programme.
Building stuck at approvals?
Send the documents you have — we will say what is missing and in what order to proceed.
Contact →Quote request
Leave your phone number; the relevant division will contact you.